Which input to the Manage Stakeholder Engagement proces… seenagape 8 years ago Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can bestbe involved in a project? A. Feedback analysis B. Stakeholder analysis C. Communication management plan D. Stakeholder management plan ← Previous question Next question →