Which input to Collect Requirements is used to identify… seenagape 8 years ago Which input to Collect Requirements is used to identify stakeholders who can provide information onrequirements? A. Stakeholder register B. Scope management plan C. Stakeholder management plan D. Project charter ← Previous question Next question →