Which index is the calculated projection of cost perfor… seenagape 8 years ago Which index is the calculated projection of cost performance that must be achieved on the remaining work tomeet a specified management goal? A. Estimate at completion B. Cost performance C. Schedule performance D. To-complete performance ← Previous question Next question →