Which illustrates the connection between work that needs to be done and its project team members?

Which illustrates the connection between work that needs to be done and its
project team members?

A.
Workbreakdown structure (WBS)

B.
Network diagrams

C.
Staffing management plan

D.
Responsibility assignment matrix (RAM)