PMI Exam Questions

Which group is formally chartered and responsible for r…

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting
changes to the project and for recording and communicating decisions?

A.
Project team

B.
Focus group

C.
Change control board

D.
Project stakeholders