Which estimating technique uses the actual costs of previous similar projects as a basis for estimat seenagape 10 years ago Which estimating technique uses the actual costs of previous similar projects as abasis for estimating the costs of the current project? A.Analogous B.Parametric C.Bottom-up D.Top-down ← Previous question Next question →