Which estimating technique uses the actual costs of pre… seenagape 8 years ago Which estimating technique uses the actual costs of previous similar projects as a basis for estimating thecosts of the current project? A. Analogous B. Parametric C. Bottom-up D. Top-down ← Previous question Next question →