Which earned value management (EVM) metric is a measure of the cost efficiency of…?

Which earned value management (EVM) metric is a measure of the cost efficiency of
budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and
is considered a critical EVM metric?

A.
Cost variance (CV)

B.
Cost performance index (CPI)

C.
Budget at completion (BAC)

D.
Variance at completion (VAC)