Which earned value management (EVM) metric is a measure of the cost efficiency of
budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and
is considered a critical EVM metric?

A.
Cost variance (CV)
B.
Cost performance index (CPI)
C.
Budget at completion (BAC)
D.
Variance at completion (VAC)