Which Control Scope input is compared to actual results to determine if corrective action is require seenagape 9 years ago Which Control Scope input is compared to actual results to determine if correctiveaction is required for the project? A.Scope baseline B.Scope management plan C.Change management plan D.Cost baseline ← Previous question Next question →