PMI Exam Questions

which communication technology factor?

A project manager managing a cross-cultural virtual project team across several time zones should be
concerned about the impacts of which communication technology factor?

A.
Urgent information need

B.
Sensitivity of information

C.
Project environment

D.
Ease of use