Which benefit measurement method considers the value of each time period’s return for a projec

[tagged]
Which benefit measurement method considers the value of each time period’s return for a project that will create deliverables over multiple time periods?

A.
Net present value

B.
Future value

C.
Present value

D.
Cost-Benefit ratio