Which Activity Duration Estimating technique incorporates additional timing for contingency purposes admin 11 years ago Which Activity Duration Estimating technique incorporates additional timing for contingency purposes? A.Analogous Estimating B.Expert Judgment C.Optimistic Estimates D.Reserve Analysis ← Previous question Next question →