You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you’ve completed this process, you’ll produce all of the following as part of the risk register update output except which one?
A.
Probability of achieving time and cost estimates
B.
Watch list of low-priority risks
C.
Priority list of risks
D.
Risks grouped by categories
Explanation:
Probability of achieving time and cost estimates is an update that is produced from the Quantitative Risk Analysis process.