When the project team directs staff assignments, which of the following is not considered in the sel

When the project team directs staff assignments, which of the following is not considered in the selection of a staff?

A.
Previous experience

B.
staff age

C.
Availability

D.
Personal interest

Explanation:
Staff age is not considered in the selection of a staff