When cost variance is negative and schedule variance is… seenagape 8 years ago When cost variance is negative and schedule variance is positive, the project is: A. under budget and behind schedule. B. over budget and ahead of schedule. C. on schedule. D. complete; all planned values have been earned. ← Previous question Next question →