When cost variance is negative and schedule variance is positive, the project is:

When cost variance is negative and schedule variance is positive, the project is:

A.
under budget and behind schedule.

B.
over budget and ahead of schedule.

C.
on schedule.

D.
complete; all planned values have been earned.