When cost variance is negative and schedule variance is positive, the project is: seenagape 9 years ago When cost variance is negative and schedule variance is positive, the project is: A.under budget and behind schedule. B.over budget and ahead of schedule. C.on schedule. D.complete; all planned values have been earned. ← Previous question Next question →