When a project in your program is completed, who will need to sign the certificate of completion?

[tagged]
You are the program manager for your organization. When a project in your program is completed, who will need to sign the certificate of completion?

A.
The project manager

B.
The program customer

C.
The program stakeholders

D.
The project management team