Neil works as a project manager for SoftTech Inc. He is working with Tom, the COO of his
company, on several risks within the project. Tom understands that through qualitative analysis
Neil has identified many risks in the project. Tom’s concern, however, is that the priority list of
these risk events are sorted in “high-risk,” “moderate-risk,” and “low-risk” as conditions apply
within the project. Tom wants to know that is there any other objective on which Neil can make the
priority list for project risks. What will be Neil’s reply to Tom?
A.
Risks may be listed by the additional analysis and response
B.
Risk may be listed by the responses in the near-term
C.
Risks may be listed by priority separately for schedule, cost, and performance
D.
Risks may be listed by categories