You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it
was not effective. What type of plan should you as a project manager will create for
implementation if a selected risk strategy fails to be fully effective?
A.
Mitigation management plan
B.
Mitigation plan
C.
Fallback plan
D.
Risk response plan