PMI Exam Questions

What type of plan should you as a project manager will create for implementation if a selected risk

[tagged]
You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it
was not effective. What type of plan should you as a project manager will create for
implementation if a selected risk strategy fails to be fully effective?

A.
Mitigation management plan

B.
Mitigation plan

C.
Fallback plan

D.
Risk response plan