What type of analysis of the risks provides a quick and high-level review of each identified risk ev

[tagged]
You and your project team have identified the project risks and now are analyzing the probability
and impact of the risks. What type of analysis of the risks provides a quick and high-level review of
each identified risk event?

A.
A risk probability-impact matrix

B.
Quantitative risk analysis

C.
Seven risk responses

D.
Qualitative risk analysis