What term is assigned to the new risks that a risk response has created? seenagape 12 years ago [tagged]A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created? A.Reactionary risks B.Chain risks C.Secondary risks D.In flux risks ← Previous question Next question →