You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?
A.
Create WBS
B.
Verify Scope
C.
Value analysis
D.
Control Scope
Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.