What should you do next?

You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

A.
Create WBS

B.
Verify Scope

C.
Value analysis

D.
Control Scope

Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.