What should be your concern? seenagape 10 years ago Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days.What should be your concern? A.There is a cost under run. B.There is a cost overrun. C.May not meet deadline. D.The project is 20 days behind schedule. ← Previous question Next question →