What should be your concern?

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work days.
What should be your concern?

A.
There is a cost under run.

B.
There is a cost overrun.

C.
May not meet deadline.

D.
The project is 20 days behind schedule.