What should be used to calculate the forecast? seenagape 8 years ago As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. Whatshould be used to calculate the forecast? A. BAC B. EAC C. ETC D. WBS ← Previous question Next question →