A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80
workdays. What should be the concern?

A.
Thereis a cost underrun.
B.
Thereis a cost overrun.
C.
The project may not meet the deadline.
D.
Theproject is 20 days behind schedule.