PMI Exam Questions

What project management term would you associated with a predetermined budgetyou’re your progr

[tagged]
What project management term would you associated with a predetermined budgetyou’re your program?

A.
Program governance

B.
Constraint

C.
Cost baseline

D.
Assumption