PMI Exam Questions

What project management plan will document the time frame and frequency for the distribution of requ

What project management plan will document the time frame and frequency for the distribution of
required information?

A.
Scope Management Plan

B.
Communications Management Plan

C.
Stakeholder Management Plan

D.
Schedule Management Plan

Explanation:
The project’s Communications Management Plan defines what information will be distributed,
when it will be distributed, to whom it will be distributed, and the modality of the information.
Answer option D is incorrect. The Schedule Management Plan defines the project work, when the
project work will happen, resource utilization, and how the schedule will be monitored and
controlled.
Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder
Management Plan.
Answer option A is incorrect. The project’s Scope Management Plan defines how the scope will be
created, how the changes will be allowed, how the scope will be executed, monitored and
controlled, and finally closed.