What project management plan is most likely to direct the quantitative risk analysis process for a p

[tagged]
What project management plan is most likely to direct the quantitative risk analysis process for a
project in a matrix environment?

A.
Risk analysis plan

B.
Staffing management plan

C.
Human resource management plan

D.
Risk management plan