What program management document should serve as the baseline for all future program decisions?

[tagged]
You are the program manager for your company and management wants you to identify how you’ll make decisions in the program planning processes. What program management document should serve as the baseline for all future program decisions?

A.
Program budget

B.
Program management plan

C.
Program scope statement

D.
Program requirements