What positive risk response has happened in this instance?

Eric is the project manager of the MTC project for his company. In this project a vendor has
offered Eric a sizeable discount on all hardware if his order total for the project is more than
$125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost
savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement
the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other
project managers in the organization, and asks if she needs any hardware for their projects. Both
Amy and Allen need hardware and they agree to purchase the hardware through Eric’s
relationship with the vendor. What positive risk response has happened in this instance?

A.
Sharing

B.
Exploiting

C.
Transference

D.
Enhancing