PMI Exam Questions

what portion of a project are risk and opportunities greatest and require intense planning and antic

In what portion of a project are risk and opportunities greatest and require intense planning and
anticipation of risk events?

A.
Closing

B.
Planning

C.
Initiating

D.
Executing