PMI Exam Questions

what point in the project is the risk of failing to achieve the project objectives the greatest?

[tagged]
At what point in the project is the risk of failing to achieve the project objectives the greatest?

A.
During project planning

B.
During the project execution

C.
At the project start

D.
At the end of the project