Joan is the project manager of the BTT project for her company. She has worked with her project
to create risk responses for both positive and negative risk events within the project. As a result of
this process Joan needs to update the project document updates. She has updated the
assumptions log as a result of the findings and risk responses, but what other documentation will
need to be updated as an output of risk response planning?
A.
Scope statement
B.
Lessons learned
C.
Risk Breakdown Structure
D.
Technical documentation