what is the team’s velocity? seenagape 9 years ago Following chart lists stories for a release of an Agile project; If the team completes Story A,Story B, and 50% of Story C for the first iteration, what is the team’s velocity? A. 10 B. 12 C. 15 D. 9 ← Previous question Next question →