What is the status of the project whose data is shown in the following S-curve?

What is the status of the project whose data is shown in the following S-curve?

A.
Under budget and ahead of schedule

B.
Over budget and behind schedule

C.
Over budget and ahead of schedule

D.
Under budget and behind schedule