what is the schedulevariance (SV) for Task 8? seenagape 9 years ago The following chart contains information about the tasks in a project. Based on the chart, what is the schedulevariance (SV) for Task 8? A.-2,000 B.-1,000 C.1,000 D.2,000 ← Previous question Next question →