What is the schedule performance index (SPI) using the … seenagape 8 years ago What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC =$80,000 EV = $40,000 A. 1 B. 0.4 C. 0.5 D. 0.8 ← Previous question Next question →