What is the schedule performance index (SPI) using the following data? admin 11 years ago What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000 A.1.00 B.0.40 C.0.50 D.0.80 ← Previous question Next question →