What is the schedule performance index (SPI) using the following data? seenagape 9 years ago What is the schedule performance index (SPI) using the following data? BAC =$100,000 PV = $50,000 AC = $80,000 EV = $40,000 A.1 B.0.4 C.0.5 D.0.8 ← Previous question Next question →