what is the schedule performance index (5PI) for Task 4? seenagape 9 years ago The following chart contains information about the tasks in a project. Based on the chart, what is the schedule performance index (5PI) for Task 4? A.0.83 B.0.9 C.1.11 D.1.33 ← Previous question Next question →