What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is
moderate (0.20)?

A.
0.03

B.
0.06

C.
0.10

D.
0.50