PMI Exam Questions

What is the formula to determine earned value (EV) for a program?

What is the formula to determine earned value (EV) for a program?

A.
Percent complete times percent remaining in the program

B.
Percent completes time the program cost estimate

C.
Percent complete times the program budget at completion

D.
Percent complete times the program cost of labor and materials