PMI Exam Questions

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual
cost (AC) is $50, and the earned value (EV) is $25?

A.
$50

B.
$100

C.
$125

D.
$175