what is the cost variance (CV)? seenagape 12 years ago If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)? A..99 B.-$2,500 C.$2,500 D.1.02 ← Previous question Next question →