what is the cost variance (CV) for Task 6? seenagape 8 years ago The following chart contains information about the tasks in a project. Based on the chart, what is the cost variance (CV) for Task 6? A. -2,000 B. 0 C. 1,000 D. 2,000 ← Previous question Next question →