what is the cost performance index (CPI) for Task 2? seenagape 8 years ago The following chart contains information about the tasks in a project. Based on the chart, what is the cost performance index (CPI) for Task 2? A. 0.8 B. 1 C. 1.25 D. 1.8 ← Previous question Next question →