What is one of the MAJOR outputs of activity sequencing? seenagape 8 years ago What is one of the MAJOR outputs of activity sequencing? A. Responsibility assignment matrix B. Work breakdown structure update C. Project network diagram D. Mandatory dependencies list ← Previous question Next question →