What-if scenario analysis is done as a part of __________ process.

What-if scenario analysis is done as a part of __________ process.

A.
Sequence Activities

B.
Develop Schedule

C.
Control Schedule

D.
Define Activities

Explanation:
B is the correct answer. What-If Scenario Analysis is an analysis for the question “What if the situation represented by scenario ‘X’ happens? “. It is part of Develop Schedule.